“………Mineweb has been detailing the enormity of this project of transforming a large underground mine into a massive open cut – particularly with there being a sterile cover of between 300-400 metres. However, the price for the development has escalated in the past eight years from original projections of about US$S3 billion, in itself a daunting figure for many mining companies….It has been long known that removal of the overburden and rock will create “mountains” in a landscape that is virtually a pancake. Now, Gottliebsen said the rock storage facility covers 6,720 hectares and eventually will be 150 metres high. “By 2050, when the mine has not even completed half its life, the pit will be 4.1 kilometres long, 3.5 km wide and 1 km deep,” …”.  Mineweb, 18 May 11

May 18, 2011 - Posted by | South Australia, uranium, wastes |