South Australian Premier announces Solar thermal power plant for Port Augusta

Solar thermal power plant announced for Port Augusta ‘biggest of its kind in the world’,  ABC, 15 August 17, A 150-megawatt solar thermal power plant has been secured for Port Augusta in South Australia, State Premier Jay Weatherill has announced.

Construction of the $650 million plant will start in 2018.

Concentrated Solar Power Simple Explanation

Aurora facts:

  • 150-megawatt solar thermal power with eight hours of storage
  • Plant will deliver 495 gigawatt hours of power annually, or 5 per cent of SA’s energy needs
  • Equivalent to powering more than 90,000 homes
  • Located 30 kilometres north of Port Augusta
  • Company says it is “completely emission free”

Mr Weatherill said the Aurora Solar Energy Project would be ready to go in 2020 and would supply 100 per cent of the State Government’s needs.

The Government will pay a maximum of $78 per megawatt hour.

Mr Weatherill said the solar thermal plant was “the biggest of its kind in the world”.

“Importantly, this project will deliver more than 700 jobs, with requirements for local workers,” he said…….

A 150-megawatt solar thermal power plant has been secured for Port Augusta in South Australia, State Premier Jay Weatherill has announced.

Construction of the $650 million plant will start in 2018.

Mr Weatherill said the Aurora Solar Energy Project would be ready to go in 2020 and would supply 100 per cent of the State Government’s needs.

The Government will pay a maximum of $78 per megawatt hour.

Mr Weatherill said the solar thermal plant was “the biggest of its kind in the world”.

“Importantly, this project will deliver more than 700 jobs, with requirements for local workers,” he said.

Mirrors to direct sunlight onto tower

Solar thermal uses heliostats, or mirrors, to concentrate sunlight onto a tower that heats molten salt. The heat created is then used to generate steam.

Solar Reserve said the plant will be able to provide between eight and 10 hours of storage and had no requirement for gas or oil generated electricity as a backup.

It is expected to employ 50 full-time workers on an ongoing basis once it is operational.

The company said the power station will operate in a similar fashion to a coal or gas station, meaning many of the jobs would “require the same skill sets”.

Mr Smith said he looked forward to supporting “federal and state renewable energy targets”. http://www.abc.net.au/news/2017-08-14/solar-thermal-power-plant-announcement-for-port-augusta/8804628

Advertisements

August 16, 2017 - Posted by | solar, South Australia

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: