Decades overdue Ranger Uranium Mine rehabilitation plan released The world is watching

Northern Land Council, 5 June 2018     The Northern Land Council and Gundjeihmi Aboriginal Corporation welcome today’s public release of the Ranger Mine Closure Plan by Energy Resources of Australia. The plan is decades overdue and critical to the company meeting the objectives of rehabilitation.

The NLC and GAC, representing the Mirarr Traditional Aboriginal Owners of the mine site, will now review the plan and engage with stakeholders as part of the approval process. While not part of a public environmental impact statement process, the public release of the plan does provide the broader community with an opportunity to comment on the plan to the Australian government.

The Mine Closure Plan is of a very high level and even though Ranger’s closure is imminent, a significant amount of detailed planning and supporting studies remain outstanding. ERA and its parent company Rio Tinto must clearly demonstrate that they have sufficient resources devoted to mine closure to provide stakeholders with confidence that the objectives outlined in the closure plan can be met.

The Ranger plan remains unenforceable until it is approved by the federal Minister for Resources. The mine’s operational life must cease by January 2021, ahead of five years’ rehabilitation. The future of Aboriginal communities downstream of the mine and the World Heritage listed values of Australia’s largest national park are at stake.

ERA and Rio Tinto’s rehabilitation obligations include remediation of the site such that it can be incorporated in the surrounding Kakadu National Park. The final determination as to whether the area can be incorporated into the World Heritage area sits with the UNESCO World Heritage Committee, on advice from its expert advisory bodies the International Union for Conservation of Nature (IUCN) and International Council on Monuments and Sites (ICOMOS).

NLC contact: Martha Tattersall 0427 031 382 GAC contact: Kirsten Blair 0412 853 641

http://gac-v3.katalyst.com.au/media/W1siZiIsIjIwMTgvMDYvMDQvM3plYWpidjJ1al8yMDE4MDQwNl9HQUNfTkxDX3JlX0VSQV9SVU1fTUNQXzVfSnVuZV8yMDE4LnBkZiJdXQ/20180406%20GAC%20NLC%20re%20ERA%20RUM%20MCP%205%20June%202018.pdf

June 6, 2018 - Posted by | Northern Territory, uranium, wastes

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: